Client
Renewable Energy Systems Ltd
Value
£16K
Preliminary Site Investigation prior to construction of 5nr Wind Turbines at Hornberget, Mala, Sweden.
The site Investigation comprised the following elements:
- Undertaking 16 trial holes to determine ground conditions
- Undertake electrical resistivity grounding surveys at turbine base and substation locations
- Land survey of new proposed access track
- Geophysical Survey at Pumping Station sites
- Laboratory testing
- Interpretative Reporting